Location: Fort Huachuca, AZ
Wattage: NA
Client: Tucson Electric Power Company
Design: May 2020
Inservice: October 2020
This project provided a stormwater analysis and developed a management plan for the current situation where a significant amount of erosion has occurred. This site has two runoff locations where water becomes concentrated flow and lifts the soils and brings them downstream as the water leaves the site. The analysis and management plan is developed for the second runoff location which flows onto eastern local streets.
The stormwater analysis used TR-55 methodology (HydroCAD) to understand the volume of runoff for the known rainfall. The 100-year storm event volume is going to be collected in a pond; the flow will travel through rip rap before reaching the bottom of the pond and start filling up.
The soils at the surface are not conducive to infiltration. An infiltration test was performed at different levels to understand the permeability of the different layers. The soils were highly permeable two to four feet below the designed pond bottom – this is where leeching basin will be utilized to promote true infiltration. The leeching basins will go below the surface four feet.
The long-term plan includes pond excavation. The site is balanced in terms of soils existing on site. The pond excavation is balanced by adding adjacent hills within the existing easement. By keeping the basin area clean the water entering the leeching basin will continue to be without sediment particles allowing infiltration to continue at high rates.